Re-submitted by the supplier to show all relevant parties have agreed and committed to the BEP. The BEP facilitates the management of delivery of the project. The post-contract BEP will develop in detail over time as more members of the supply chain are appointed. It should include:

  • A response to requirements of the EIR
  • Revised PIP
  • Responsibility Matrix
  • Details of: Management Planning and documentation
  • Methods and procedures
  • A TIDP
  • A MIDP

Adherence to the BEP should be monitored throughout the duration of the contract to ensure that the PIM is being developed in accordance with the MIDP and all relevant standards. 

A template is available Pre-Contract BIM Execution Plan is available via CPIx: CPIx Post-Contract BIM Execution Plan.pdf